Painting Complete, Fireplace Over 1/2 Done

All painting was completed Saturday. The fireplace was half done by Friday but halted over the weekend because the wood for the mantle was twisted and the support brackets weren’t sturdy enough to support it. We got new brackets and a new mantle over the weekend, and Andy worked with J to get it straight, level and hung. Kenny, our stone guy, will finish the stone on it this week, along with the remainder of the exterior.

Wood flooring is being delivered today so it can sit in the house for a week. The gas got hooked up on Friday, and the heater is now on. Outlet covers and lights should go in this week. Nate, our tile guy, should finish all tile this week too. The wood flooring will be installed beginning next Monday. Cabinets after that, then countertops, etc.