House Build Progress

House Build Progress

I haven’t posted in a while because things felt like they were at a standstill for about a month. Everything is finally moving again. All of the following occurred within the last two weeks: Gas trench dug and ready to be tied in Electric tied into house All windows now in All doors except basement door are now in Insulation complete Deck will be completed today Part of the siding is complete – and currently in progress Drywall is supposed to be delivered today and installers should be here tomorrow.Everything from here forward is FINISH WORK! Oh my goodness, oh my...
Electric, Plumbing, HVAC Complete

Electric, Plumbing, HVAC Complete

Well, I haven’t posted in a while because its all been important but boring infrastructure work that’s been done. Electric, plumbing and HVAC work is now complete. Garage floor poured today (pics tomorrow). Doors next week, insulation, drywall and deck after that, and we’ll be on to finish work! OMG!...